04.03.2025

Replacement of a standby UPS.

Over the period from November 2024 to January 2025, the AO ASC engineers have performed a range of construction and erection and commissioning works on replacement of a standby uninterruptible power source, having a capacity of 120 kVA, designed for electrical equipment of car tippler No.2, building grid line «Б», the customer — AO Eastern port (Joint Stock Company). The works were carried out without stoppage in existing production under conditions of a tight operating schedule of the coal terminal on the eve of Christmas holidays.  

As part of the works mentioned the cables were laid, the UPS cabinet Powercom VGD-II-150M33В was installed, as well as the power modules Powercom VGD-II-PM25M — 5 pcs., the service bypass cabinet ЩИБП-160 315А IP54/66, the battery module ШБ2 40-620W, the accumulator batteries – 40 pcs., and the adapter for monitoring the UPS condition via IP network SNMP Powercom 1-port internal NetAgent (DA807) USB. Upon completion of the commissioning works the equipment was put into operation.

The customer was provided with a complete set of operating documentation. The UPS equipment operates flawlessly at the moment. 

Метки:
To other news