Completion of a set of works on upgrading the automation system for filters of jaw breakers, hammer crushers and clinker mills No.202 and No.203.
The purpose of upgrading was to replace the worn-out and obsolete electrical equipment and automated control system while maintaining the scope of application and sustaining the ratings of the equipment used.
The following activities were performed as part of the project:
- — S7-2000 controllers were replaced with S7-1200 controllers, and a new control software was developed;
- — the start-control devices were replaced;
- — a set of works on integration of compressor units into the APCS was performed;
- — the operator workstation at filters of clinker mills No.202 and No.203 was replaced; a new vision software — WinCC was installed instead of a previously installed one — Software Promotic (the Czech Republic);
- — the operator workstations with vision software WinCC were installed at filters of jaw and hammer breakers;
- — the installation works to the extent of new cable route laying were executed with the involvement of subcontracting organization OOO Areal (Limited Liability Company).